Investor: Housing and Urban Development Investment Corporation (HUD Group).
Project implementation location: Nghia Chanh ward and Nghia Dong commune, Quang Ngai city, Quang Ngai province.
Implementation period: from 2019 to 2021
Scale: the total area is about 170 hectares.
Scope of work performed:
– Construction of contract package No. NLK-03/19: Construction of rough construction and finishing of the exterior from apartment No. 46 to Unit 58 (total 13 units) Lot LK-03.
– Construction of contract package No. NLK-04/19: Construction of rough construction and exterior finishing from apartment 33 to apartment 45 (total 13 units) Lot LK-04
– Construction of package number TNT-LH-01/19: Construction of wastewater drainage system and pavement of 16ha area.


Pictures of construction of technical infrastructure items

Pictures of sidewalk construction

Construction of drainage system
This is the first new urban area project of the Housing and Urban Development Investment Corporation (HUD Group) deployed in the Central region. The project is a complex of low-rise buildings, villas, commercial service works associated with parks and lakes. In addition, in this urban area, a part of the area is reserved to serve the households in the planning area who need to be relocated; building social houses, housing for low-income people.

Construction of underground water tank


Construction image of reinforced concrete column system


Fabrication and erection of floor reinforcement

Construction and exterior finishing work



Ready for the Owner to hand over to the customer
Up to now, the remaining works of the basic bidding packages have been completed, the Company is working with related parties to conduct the review, acceptance and handover of work items in accordance with the signed contract.