Investor: Nam Ban 2 Hydropower Company Limited Project
Implementation location: Nam Ban commune, Nam Nhun district, Lai Chau province
Implementation period: from 2016 to 2018
Design capacity: 22MW
Scope of work performed:
– Construction of water tunnels and pressurization towers.
– Construction of a 110kV transmission line connecting to the national power grid.
– Installation of electromechanical equipment systems.

Photo of construction and installation of mechanical and electrical equipment of the factory
The project uses technology equipment system of Andritz Company (India), vertical shaft turbine technology. The company’s team of engineers and technical workers have tried their best to install equipment under the supervision of an Indian expert, a Supervision Consultant from Dong Nai 5 Hydropower Plant.

Photo of construction and installation of mechanical and electrical equipment of the factory

Photo of construction and installation of mechanical and electrical equipment of the factory
Nam Ban 2 Hydropower Project was completed after more than 2 years of construction, contributing to the national electricity system more than 80 million kWh of electricity per year and contributing to the socio-economic development of the locality. Our company is proud to have contributed a part to the success of the project.